Next week (December 19 to December 23), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site. The roof protection at USC Condo courtyard will be finished this week.
The following week (December 26 to December 30), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels.
This weekend the site will be closed on Saturday, December 17th.
Looking ahead to the upcoming holidays, the New School construction site will be closed on Saturdays, December 24 and December 31st, also on Mondays, December 26th and January 2nd.