Next week (May 28 to June 1), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building by the end of the month. We will begin pouring concrete at 6am on Friday the 25th in order to finish in a timely manner. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.
The following week (June 4 to June 8), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.