Latest New School Construction Update

Next week (June 11 to June 15), Mechanical equipment deliveries and work on them will continue at the 17th and 18th floor levels. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.

The following week (June 18 to June 22), we will be working on the machine room levels on the 17th and 18th floors. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.

This weekend the site will be open on Saturday, June 9th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day .