Next week (October 22 to October 26), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.
The following week (October 29 to November 2) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all floors. Curtain wall installation on the lower floors will proceed along 14th st. inside the construction site.
This weekend the site will be open on Saturday, October 20th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.