Next week (December 24 to December 28), material and equipment deliveries and installation work will continue on all floors inside the building. The site will be closed on December 25th for the holiday but will be open on Monday the 24th and Wednesday the 26th.
The following week (December 31 to January 4), Material and equipment deliveries and installation work will continue on all floors.
This weekend the site will be open on Saturday, December 22nd for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.