Next week (January 14 to January 18), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.
The following week (January 21 to January 25), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. We will begin dismantling the sidewalk shed on 14th street at the end of the month.
This weekend the site will be open on Saturday, January 12th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.