Next week (February 18 to February 22), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The sidewalk shed on 14th st. is scheduled to begin dismantling, pending construction progress. The site will be closed on Monday, February 18th, for the holiday.
The following week (February 25 to March 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.