Next week (April 1 to April 5), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. We will be work on the new sidewalks around the building as well.
The following week (April 8 to April 12), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. By then end of this week we plan to have the rest of the sidewalk on 14th street complete. Additionally we plan to begin removing the sidewalk shed along 5th ave.
This weekend the site will be open on Saturday, March 30th for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.