Next week (April 8 to April 12), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. We will be work on the new sidewalks around the building as well and plan on completing the 14th street side by the end of the week.
The following week (April 15 to April 19), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. Additionally we plan to begin removing the sidewalk shed along 5th ave.
This weekend the site will be open on Saturday, April 6th for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.