Next week (July 1 to July 5), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalk around the building on 13th st. Additionally we will be working on the roofs of the building. There will be no work on July 4th holiday.
The following week (July 8 to July 12), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.