Latest New School Construction Update

Next week (July 15 to July 19), material and equipment deliveries and installation work will continue on all floors inside the building. We will be working on the new sidewalk around the building on 13th st. Additionally we will be working on the roofs of the building.

The following week (July 22 to July 26), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.
This weekend the site will be open on Saturday, July 13th for interior, roof, and sidewalk activities between the work hours of 7AM and 5PM as permitted by the City.