Here’s what they’re currently saying:
“With demolition and abatement complete, Tishman Construction and the Durst Organization have moved on to the next major phases of the construction process: clearing and laying the foundation. Future deadlines include the following.”
Present to August 2011: Excavation foundation
September 2011 to May 2012: Superstructure erection
May 2012 to October 2012: Façade and building enclosure