This week (May 16 to May 20), Contractors will continue to excavate earth and rock, and load out material. We will continue to underpin the 13th Street adjacent building. Drilling of tie-backs, installation of rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Preparation for concrete foundation walls is scheduled to begin.
The following week (May 23 to May 27), we will continue line drilling, rock excavation, and loading out as well as, lagging and sheeting. Concrete foundation walls will progress.