“Next week (August 1 to August 5), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Final adjustments to the access ramp within the site are ongoing. As early as Thursday, July 28th, the construction fence along the North end Fifth Avenue will be relocated to the curb line with pedestrians diverted to a walkway in the street as approved by the Department of Transportation. The following week (August 8 to August 12 ), we will continue with concrete foundation walls, line drilling, rock excavation, and loading out, as well as lagging and sheeting. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, July 30th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.”