Looking ahead to the upcoming holiday, the New School construction site will be closed on Saturday, December 31st and also on Monday, January 2nd. Next week (January 2 to January 6), Superstructure and concrete work will continue at 2nd and 3rd floor levels. Sidewalk sheds will continue being erected around the perimeter of the site and we will be opening the one on 14th st. The following week (January 9 to January 13), we will continue superstructure concrete and slabs on 2nd and 3rd floor levels. In the upcoming weekend, January 14th, we plan on installing the new crane on Fifth Avenue.