Next week (January 16 to January 20), Superstructure work will continue at and 3rd, 4th and 5th floor levels. Sidewalk shed along 14th Street has been opened and we will open the sidewalk shed along 5th ave completing the sidewalk shed work.
The following week (January 23 to January 27), we will continue superstructure concrete and slabs on 3rd, 4th and 5th floor levels.
This weekend the site will be open on Saturday, January 14th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
In addition to the normal work this Saturday we will be installing a new crane on 5th Ave. that will service the site for the duration of the project. During the installation 13th St. will be closed as well as some lanes on 5th Ave.