Next week (February 20 to February 24), Superstructure work will continue at 5th and 6th floor levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (February 27 to March 2), we will continue superstructure concrete and slabs on the 5th and 6th floor levels. Deliveries will continue to arrive at the site. The site will not be open on Monday the 20th, Presidents’ Day holiday.
This weekend the site will be open on Saturday, February 18th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.