DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June.
Therefore, next week (April 30 to May 4), Superstructure work will continue at the 15th and 16th floor levels. Tuesday, May 1st and Friday, May 4th we will have a pour with a 6 am start time and similar end time, weather permitting. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 7 to May 11), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be closed.