Next week (October 8 to October 12), Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation on upper floors will continue. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The crane that is on site will remain for the duration of curtain wall installation and will not affect pedestrian or automotive traffic.
The following week (October 15 to October 19) Material and equipment deliveries and installation work will continue on all floors. Curtain wall installation will continue on all upper floors. Curtain wall installation on the lower floors will proceed along 5th ave inside the construction site. The site will be open on Monday the 8th.
This weekend the site will be open on Saturday, October 6th for superstructure related activities and curtain wall installation between the work hours of 7AM and 5PM as permitted by the City. Con Ed will be working in the street.