Next week (January 28 to February 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.
The following week (February 4 to February 8), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.
This weekend the site will be open on Saturday, January 26th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.