Next week (February 25 to March 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. We have begun dismantling the construction hoist on the building exterior and will continue to do so for the upcoming weeks.
The following week (March 4 to March 8), material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.
This weekend the site will be open on Saturday, February 23rd for interior, superstructure, sidewalk, and hoist removal related activities between the work hours of 7AM and 5PM as permitted by the City.