Next week (June 24 to June 28), material and equipment deliveries and installation work will continue on all floors inside the building. Additionally we will be working on the roofs of the building.
The following week (July 1 to July 5), material and equipment deliveries and installation work will continue on all floors as well as sidewalk work.