Latest New School Construction Update

Next week (October 7 to October 11), material and equipment deliveries and installation work will continue on the academic floors inside the building. Additionally we will be using a lift on the sidewalk to wash the exterior of the building.

The following week (October 14 to October 18), material and equipment deliveries and installation work will continue on academic floors.

This weekend the site will be open on Saturday, October 5th for interior activities between the work hours of 7AM and 5PM as permitted by the City.