August 2011

You are currently browsing the monthly archive for August 2011.

The New School says:

Next week (August 29 to September 2), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers and line drilling will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work and underground electrical and plumbing will proceed. Contractors will be removing the interior earth ramp. A small cherry picker crane will be delivered to the site next week and will be stationed inside the Construction fence. This crane will remain there for approximately two months.

The following week (September 6 to September 9 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, interior core foundation work, and underground electrical and plumbing. Concrete pours for the slab on grade are anticipated to start this week. The site will be closed for Labor Day weekend (Saturday, Sept. 3 through Monday, Sept. 5).

DEP will continue to repair the water main along 13th Street. As part of this work, the DEP may periodically shut water service off. This work is out of our control.

The main thing to do to prep for Hurricane Irene is to remove anything from outside your apartment–on roof spaces or fire escapes–that could blow away in heavy and sustained winds. Please do this ASAP.

Signage indicates that a new, and rather large, Greek restaurant will be setting up shop on the east side of University Place around 10th Street.

Next week (August 22 to August 26), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 29 to September 3 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street.

Carnival, the nightclub atop Bowlmor Lanes, will be transformed into a mini-golf nightclub called The Greenwich Village Country Club in October.

Next week (August 15 to August 19), contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 22 to August 26 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out, and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, August 13th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

Community Board #3 has voted overwhelmingly to support designation of the proposed East Village/Lower East Side and East 10th Street Historic Districts. This is a major step towards preservation of the irreplaceable and increasingly threatened historic resources and character of the East Village. However, the Landmarks Preservation Committee must still approve the move.

Next week (August 8 to August 12), Contractors will continue to excavate earth and rock, and load out material. Installation of bracing rakers, line drilling, lagging and sheeting around the perimeter will progress as well. Concrete foundation walls will continue along the perimeter of the site. Interior core foundation work will proceed. The following week (August 15 to August 19 ), we will continue with concrete foundation walls, line drilling, rock excavation, loading out,and interior core foundation work & underground plumbing. DEP will continue to work on the water main along 13th Street. The site will be open on Saturday, August 6th. Work hours are between 9AM and 5PM as permitted by the City. To control noise levels, work activities will be limited to the placement of formwork and rebar for concrete placement, wood lagging, and installation of walers and braces. There will be no rock excavation, rock chopping, or hauling on Saturday.

The neighborhood is more fun now that crazy chef Eddie Huang’s Baohaus 2 is open on 14th between 2nd and 3rd. A bao is a little Chinese sandwich usually stuffed with some kind of pork. The inventive and very funny Huang, who has Taiwanese roots, is making many variations on the theme, plus coming up with all kinds of other funky Chinese home cooking. Check it out.

World of Weiners

Sausage Inc. has opened the doomed space on University between 12th and 13th that has housed a bakery, a Philly Cheesesteak shop and Wok New York.