The former Manhattan Kids’ Club on East 13th St. on our block is being renovated and will become a branch of Utrecht Art Supplies, perfect for all those New School students who study art in that same building.
You are currently browsing the monthly archive for May 2012.
Next week (June 4 to June 5), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (June 11 to June 15), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The crane on site will be demobilized and removed from site at the end of June.
This weekend the site will be open on Saturday, June 2nd for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise.
Next week (May 28 to June 1), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building by the end of the month. We will begin pouring concrete at 6am on Friday the 25th in order to finish in a timely manner. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.
The following week (June 4 to June 8), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
Rumor has it that the parking garage directly across from us at 12 East 13th St. is for sale and could be converted into offices, a hotel, or most likely 17 to 20 luxury condos. More construction to come????
The last piece of structural steel has been installed at the top of the New School building.
Next week (May 21 to May 25), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 28 to June 1), we will be working on the machine room levels on the 18th floor. Additionally we will have another crane on the Northwest corner of the site to help with a steel truss installation. This should not greatly affect pedestrian or road traffic. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic. The site will be closed on Monday, May 28th for the Memorial Day Holiday.
This weekend the site will be open on Saturday, May 19th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.
To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work there will be a crew on 14th st. working on the Con Ed site connections.
Next week (May 14 to May 18), Superstructure work will continue at the 18th floor level. The superstructure concrete work will be completed on the building buy the end of the month. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 21 to May 25), we will be working on the machine room levels on the 18th floor. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, May 12th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. There will be steel work being done on the 5th Ave. side of the building. As a result there will be another crane on site to lift the pieces into place but it will sit in the site and will not affect pedestrian or motor traffic in the area.
Additionally, Con Ed will be doing street connections on 14th street.
DOB has granted our request to start placing our concrete at 6am, which will allow us to finish this work earlier in the evening. We have 3 more instances like this until we finish our superstructure in early June. Friday, May 4 we will have a pour at the 16th floor with a 6am start time and similar end dime, weather permitting.
Therefore, next week (May 7 to May 11), Superstructure work will continue at the 17th floor level. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
The following week (May 14 to May 18), we will continue superstructure concrete and slabs on the 17th floor and roof levels. Deliveries for the internal systems of the building have been ongoing and will continue, although they should not greatly affect the flow of pedestrian and road traffic.
This weekend the site will be open on Saturday, May 5th for superstructure related activities between the work hours of 7AM and 5PM as permitted by the City. To control noise levels within the site, work activities will be limited to the placement of formwork and concrete, plumbing and electrical work, rebar for concrete placement, using the crane and equipment to support all activities. Safety horns are used, and required by law, to coordinate lifting with the crane and to alert the workers of the danger overhead. We have directed the operators to limit the use of horns to one short sounding and to use the crane later in the day so as to avoid any excess noise. In addition to the normal work on the job site, we will have an additional crane on site at 5th ave. to install the stair trusses on the west side of the building. The crane will be completely on site and should not interfere with pedestrian or automotive traffic in the area.