Next week (January 28 to February 1), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

The following week (February 4 to February 8), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

This weekend the site will be open on Saturday, January 26th for interior, superstructure and sidewalk related activities between the work hours of 7AM and 5PM as permitted by the City.

Next week (January 21 to January 25), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building. The site will be closed for the holiday on Monday, the 21st.

The following week (January 28 to February 1), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work.

This weekend the site will be open on Saturday, January 19th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

Next week (January 14 to January 18), material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work. Additionally we will begin work on the new sidewalks around the building.

The following week (January 21 to January 25), Material and equipment deliveries and installation work will continue on all floors and roofs as well as sidewalk work. We will begin dismantling the sidewalk shed on 14th street at the end of the month.

This weekend the site will be open on Saturday, January 12th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.

Click here to see 21 archival photos of Union Square dating back as far as 1888.

Next week (January 7 to January 11),interior building material and equipment deliveries and installation work will continue on all floors inside the building as well as roof work.

The following week (January 14 to January 18),interior building material and equipment deliveries and installation work will continue on all floor as well as roof work.

This weekend the site will be open on Saturday, January 5th for interior and superstructure related activities between the work hours of 7AM and 5PM as permitted by the City.